Welcome to the client portal. Please see the latest progress for your home. You can request an update by using the button below.

Project Manager: Brett  

Site Supervisor: Brett

Image.jpeg
Image.jpeg
Image2.jpeg

Latest Announcement

14/06

Tilers will be finished this week.

Electrical fit off is 90% complete, they are just waiting on the splash backs and a few other bits to complete.

Heating and cooling fit off complete - just needs to be commissioned once elec and plumbing fit offs are completed.

Plumbing fit off late this week.

Roller door and panel lift door install this week also.

 

Flooring and first clean to follow - awaiting confirmation of installation with the new vinyl selection

Externally - Down pipes are all on just waiting some timely weather to get storm water done and connected

External concrete to alfresco and driveway to follow

Timeline

Please note dates are subject to change due to unforeseen circumstances