Welcome to the client portal. Please see the latest progress for your home. You can request an update by using the button below.

Project Manager: Brett  

Site Supervisor: Brett

Image.jpeg
Image.jpeg
Image2.jpeg

Latest Announcement

14/06

Tilers will be finished this week.

Electrical fit off is 90% complete, they are just waiting on the splash backs and a few other bits to complete.

​

Heating and cooling fit off complete - just needs to be commissioned once elec and plumbing fit offs are completed.

​

Plumbing fit off late this week.

​

Roller door and panel lift door install this week also.

 

Flooring and first clean to follow - awaiting confirmation of installation with the new vinyl selection

Externally - Down pipes are all on just waiting some timely weather to get storm water done and connected

​

External concrete to alfresco and driveway to follow

​

Timeline

Please note dates are subject to change due to unforeseen circumstances