Latest Announcement
14/06
Tilers will be finished this week.
Electrical fit off is 90% complete, they are just waiting on the splash backs and a few other bits to complete.
​
Heating and cooling fit off complete - just needs to be commissioned once elec and plumbing fit offs are completed.
​
Plumbing fit off late this week.
​
Roller door and panel lift door install this week also.
Flooring and first clean to follow - awaiting confirmation of installation with the new vinyl selection
Externally - Down pipes are all on just waiting some timely weather to get storm water done and connected
​
External concrete to alfresco and driveway to follow
​
Timeline
Please note dates are subject to change due to unforeseen circumstances